Electrical Abstract- NBC- (Part-2)

 

Luminous Efficacy, Lumen Maintenance and Color Rendition (Table-8) NBC

Light Source WattageEfficacy (lm/W )Average LifeMaintenanceColor Rendition
Incandescent lamps 15 to 200 12 to 20 500 to 1000 Fair to good Very good
Tungsten halogen    300 to 1500 20 to 27 200 to 2000 Good to very good Very good
Standard fluorescent lamps      20 to 8055 to 655000Fair to good Good
Compact fluorescent lamps (CFL)      5 to 40 60 to 707500GoodGood to very good
Slim line fluorescent     18 to 5857 to 675000 Fair to goodGood
High pressure mercury vapor lamps     60 to 1000 50 to 655000 Very low to fair Federate
Blended – light lamps   160 to 250 20 to 305000Low to fair Federate
High pressure sodium vapor lamps 50 to 1000 90 to 125 10000 to 15000 Fair to good Low to good
Metal halide lamps      35 to 2000 80 to 954000 to 10000Very low Very good
Low pressure sodium      10 to 180100 to 20010000 to 20000Good to very good Poor
LED 0.5 to 2.0 60 to 100 10000Very good Good for white LED

 

Approximate Cable Current Capacity

Cable SizeCurrent CapacityMCB Size
1.5 Sq.mm7.5 To 16 A8A
2.5 Sq.mm16 To 22 A15A
4 Sq.mm22 To 30 A20A
6 Sq.mm39 To 39 A30A
10 Sq.mm39 To 54A40A
16 Sq.mm54 To 72A60A
25 Sq.mm72 To 93A80A
50 Sq.mm117 To 147A125A
70 Sq.mm147 To 180A150A
95 Sq.mm180 To 216A200A
120 Sq.mm216 To 250A225A
150 Sq.mm250 To 287A275A
185 Sq.mm287 To 334A300A
240 Sq.mm334 To 400A350A

 

Requirements  for  Physical  Protection  of Underground Cables  (As per NBC)

Protective  ElementSpecifications
Bricks (a) 100 mm minimum  width 
(b) 25 mm thick 
(c) sand cushioning 100  mm  and  sand  cover 100 mm 
Concrete slabsAt least 50 mm thick
Plastic  slabs (polymeric cover  strips) Fiber  reinforced plasticdepending on properties  and has to be matched with the protective cushioning and cover
PVC  conduit  or  PVC  pipe  or stoneware  pipe or Hume pipeThe  pipe  diameter should  be  such  so  that the  cable  is  able  to easily slip down the pipe
Galvanized pipe The  pipe  diameter should  be  such  so  that the  cable  is  able  to easily slip down the pipe
The Trench : The trench shall be back filled to cover the cable initially by 200 mm of sand fill; and then a plastic marker strip  hall be put over the full length of cable in the trench.
The Marker Signs: The marker signs shall be provided where any cable enters or leaves a building. This will identify that there is a cable located underground near the building.
 The trench shall then be completely filled. If the cables rise above ground to enter a building or other structure, a mechanical protection such as a GI pipe or PVC pipe for the cable from the trench depth to a height of 2.0 m above ground shall be provided.

 

AREA REQUIRED FOR GENERATOR IN ELECTRIC SUBSTATION (As per NBC)

Capacity  kVAArea m2Clear Height below the Soffit of the Beam m
25563.6
48563.6
100653.6
150723.6
2481004.2
3501004.2
4801004.2
6001104.6
8001204.6
10101206.5
12501206.5
16001506.5
20001506.5

 

Low Voltage Cabling for Building (As per NBC)

Low Voltage CableCables/wires, such as fiber optic cable, co-axial cable, etc. These shall be laid at least at a distance of 300 mm from any power wire or cable. The distance may be reduced only by using completely closed earthed metal trucking with metal separations for various kind of cable. Special care shall be taken to ensure that the conduit runs and wiring are laid properly for low voltage signal to flow through it.
The power cable and the signal or data cable may run together under floor and near the equipment. However, separation may be required from the insulation aspect, if the signal cable is running close to an un-insulated conductor carrying power at high voltage. All types of signal cables are required to have insulation level for withstanding 2 kV impulse voltages even if they are meant for service at low voltage.
Conduit Color SchemePower conduit=Black
Security conduit=Blue
Fire alarm conduit=Red
Low voltage conduit=Brown
UPS conduit Green

 

Sub Station Guideline (As per NBC)

Substation LocationLocation of substation in the basement should be avoided, as far as possible.
If there is only one basement in a building, the substation/switch room shall not be provided in the basement and the floor level of the substation shall not be lowest point of the basement.
Substation shall not be located immediately above or below plumbing water tanks or sewage treatment plant (STP) water tanks at the same location
Substation Door/ShutterAll door openings from substation, electrical rooms, etc, should open outwards
Vertical shutters (like rolling shutters) may also be acceptable provided they are combined with a single leaf door opening outwards for exit in case of emergency
For large substation room/electrical  room  having  multiple equipment,  two  or more  doors  shall  be provided which shall be remotely located from each other
No services or ventilation shafts shall open into substation or switch room unless specific to substation or switch room
Transformer LocationIn case of HV panel and transformers located at different floors or at a distance more than 20 m, HV isolator shall be  provided  at transformer end
In case transformer and main MV/LV panel room are located at different floors or are at a distance more than 20 m, MV/LV isolator shall be provided at  transformer  end
In  case  of  two  transformers  (dry  type  or transformers with oil quantity less than 2 000 liter)  located  next  to  each  other without intermittent wall, the distance between the two shall  be minimum  1 500 mm  for  11  kV, minimum 2 000 mm for 22 kV and minimum 2 500 mm for 33 kV. Beyond 33 kV, two transformers shall be separated by baffle wall of 4 h fire rating.
If dry type transformer is used, it may be located adjacent to medium voltage switch gear in the form of unit type substation. In such a case, no separate room or fire barrier for the transformer is required either between transformers or between transformer and the switch gear, thereby decreasing the room space requirement; however, minimum distances as specified.
Oil Filled Equipment (Transformer / C.B)Substations with oil-filled equipment/apparatus transformers and high voltage panels shall be either located in open or in a utility building
They shall not be located in any floor other than the ground floor or the first basement of a utility building  not be located below first basement slab of utility building.
They shall have direct access from outside the building for operation and maintenance of the equipment.
It shall be separated from the adjoining buildings including the main building by at least 6 m clear distance to allow passage of fire tender between the substation/utility building and adjoining building/main building.
Substation equipment having more than 2 000 liter of oil whether located indoors in the utility building or outdoors shall have  baffle walls  of  4  h  fire  rating between apparatus.
Provision of  suitable oil soak-pit, and where use of more than 9 000 liter of oil in any one oil tank, receptacle or chamber is involved, provision shall be made for the draining away or removal of any oil which may leak or escape from the tank, receptacle or chamber containing the same
Power Supply Voltagesupply  is  at  240  V  single  phase  up  to  5  kVA, 415/240 V 3-phase from 5 kVA to 100 kVA, 11 kV (or 22 kV) for loads up to 5 MVA and 33 kV or 66 kV for consumers of connected load or contract demand more than 5 MVA.
In case of connected load of 100 kVA and above, the relative advantage of high voltage three-phase supply should be considered.
In case of single point high voltage metering, energy meters shall  be  installed  in  building  premise,such a place which is readily accessible to the owner/operator of the building and the Authority. The supplier or owner of the installation shall provide at the point of commencement of supply a suitable isolating device fixed in a conspicuous position at not more than 1.7 m above the ground so as to completely isolate the supply to the building in case of emergency
Trench DrainIn case of cable trench in substation/HV switch room/MV switch room, the same shall be adequately drained to ensure no water is stagnated at any time with live cables.
Fence for SubstationEnclose any part of the substation which is open to the air, with a fence (earthed efficiently at both ends) or wall not less than 1800 mm (preferably not less than 2400 mm) in height
HV Distribution in BuildingThe power supply HV cables voltage shall not be more than 12 kV and a separate dedicated and  fire  compartmented  shaft  should  be provided for carrying such high voltage cables to upper floors in a building. These shall not be mixed with any other shaft and suitable fire detection and suppression measures shall be provided throughout the length of the cable on each floor.
Switch Room / MV switch roomSwitch room / MV switch room shall be arrived at considering 1200 mm clearance requirement from top of the equipment to the below of the soffit of the beam .In case cable entry/exit is from above the  equipment  (transformer,  HV switchgear, MV  switchgear),  height  of substation room/HV switch room/MV switch room shall also take into account requirement of space for turning radius of cable above the equipment height.

Area for Transformer Room: (As per NBC-2005):

Transformer SizeMin. Transformer Room Area (M2)Min. Total Sub Station Area( Incoming HV,LV Panel, T.C Roof) (M2)Min. Space Width (Meter)
1X160

14

90

9

2X160

28

118

13.5

1X250

15

91

9

2X250

30

121

13.5

1X400

16.5

93

9

2X400

33

125

13.5

3X400

49.5

167

18

2X500

36

130

14.5

3X500

54

172

19

2X630

36

132

14.5

3X630

54

176

19

2X800

39

135

14.5

3X800

58

181

14

2X1000

39

149

14.5

3X1000

58

197

19

  •  The Capacitor Bank should be automatic Switched type for Sub Station of 5MVA and Higher.
  • Transformer up to 25KVA can be mounted direct on Pole.
  • Transformer from 25KVA to 250KVA can be mounted either on “H” Frame of Plinth.
  • Transformer above 250KVA can be mounted Plinth only.
  • Transformer above 100MVA shall be protected by Drop out Fuse or Circuit Breaker.